Case Studies / Residential acreage / Marsden, Logan

3,100 Tonnes, Friable Asbestos

Asbestos Soil Remediation for a Homeowner in Marsden

Total Asbestos removed 3,100 tonnes of asbestos-contaminated soil and mixed demolition waste from a Marsden acreage property, using its own excavators, roller and employees to deliver a complex clean-up in wet conditions.

3,100 tContaminated soil and mixed waste removedSurveyor’s estimate was 3,000 t; final figure from waste records
~2 weeksOn site, including rain stoppagesCommenced early June 2026
<0.01 f/mLEvery air monitoring resultMonitoring report retained by Total Asbestos
LocationMarsden, Logan (Queensland)
ClientPrivate homeowner (investment property)
PropertyOccupied residential rental on acreage
MaterialAsbestos-contaminated soil mixed with timber, bricks, concrete and metal; weathered asbestos cement classified as friable by the hygienist
Quantity removed3,100 tonnes
TimingCommenced early June 2026; approximately two weeks including rain stoppages
In-house equipment20-tonne excavator, 11-tonne excavator and roller
On-site crewOne asbestos supervisor, one asbestos technician and two excavator operators (all directly employed)
HaulageApproximately ten subcontracted truck-and-quad combinations on rotation
DisposalRemondis at Swanbank
Completion documentationAsbestos clearance certificate following the hygienist’s visual inspection; air monitoring report

The Challenge: Mixed Asbestos Waste Across an Acreage Property

A homeowner contacted Total Asbestos about extensive asbestos contamination at the rear of a rented acreage property in Marsden. Demolition rubbish had built up in multiple piles and was also spread across the ground. The owner had inherited the problem: the material had been dumped on the block during a tenancy, and Logan City Council wanted it cleaned up.

The homeowner had already engaged an occupational hygienist to sample the material. The assessment identified asbestos in the rubbish, debris and soil. Weathered asbestos cement sheeting was present and, as described to the project team, the material was classified as friable. Black plastic covers and sediment-control barriers were already around the stockpiles when Total Asbestos arrived.

Aerial view of covered asbestos-contaminated demolition waste stockpiles on a Marsden acreage property before remediation
Before: the main stockpile under black plastic at the rear of the block, with more material spread across the ground.
Drone view of the Marsden acreage property showing the extent of the contaminated stockpiles
The extent of the contamination across the rear of the property.
Close aerial view of plastic-covered asbestos-contaminated stockpiles with sediment barriers in Marsden
Covers and sediment barriers were already in place before work commenced.

A Remediation Job That Needed Earthmoving Capability

The contaminated material included timber, bricks, concrete and metal bound together in sticky soil. It could not practically be separated on site, so the entire mixture had to be removed as contaminated waste. The scale of the stockpiles, the mixed material and the wet ground made this far more than a collection job. It needed excavation, temporary road construction, coordinated truck movements and a disposal arrangement able to take a very large volume of asbestos-contaminated waste.

Planning the scope and quantities

The team worked from the hygienist’s written remediation plan. A surveyor was also engaged to assess the stockpiles and estimate the quantity requiring removal. The initial estimate was about 3,000 tonnes; the final quantity removed was 3,100 tonnes, supported by the waste records held by the business.

New tenants were living at the property throughout the work. The house was at the front, with remediation taking place at the rear. Temporary fencing separated the work area from the occupied part of the property, and asbestos warning signage marked the site.

Total Asbestos removal in progress signage and danger asbestos tape on temporary fencing in Marsden
Temporary fencing and asbestos signage kept the tenants’ side of the block separate from the work area.
Total Asbestos tipper truck delivering recycled asphalt for a temporary access road on the Marsden site
Recycled asphalt being delivered to build the temporary truck route.

Building access over wet ground

Wet ground was the major practical challenge. Rather than relying on the soft surface, the team imported recycled asphalt, placed it along the truck route and compacted it with the company’s own roller. That gave the trucks a prepared pathway into the loading area, and it made the access construction part of the remediation rather than a separate problem.

In-house machinery and operators

Total Asbestos deployed its own 20-tonne excavator, 11-tonne excavator and roller. The on-site team was an asbestos supervisor, an asbestos technician and two excavator operators, all employed directly by the company. The excavators arranged material in a windrow alongside the truck route so it was positioned for loading as each truck moved through the site, keeping excavation and outgoing loads in step.

Haulage was subcontracted, with approximately ten truck-and-quad combinations operating on rotation. The waste was transported to Remondis at Swanbank, with Total Asbestos coordinating excavation and loading around the transport movements.

Total Asbestos 20-tonne excavator working a windrow of asbestos-contaminated mixed waste in Marsden
The 20-tonne excavator working the windrow beside the truck route.
Truck and quad being loaded with asbestos-contaminated waste by an excavator on the Marsden site
Around ten truck-and-quad combinations rotated through the site to Remondis at Swanbank.

Managing Rain Interruptions and Air Monitoring

The work spanned about two weeks, including weather stoppages. On days of heavy rain, slippery conditions at the receiving facility meant it could not accept further waste, and removal had to pause. The material was already damp from the weather and was kept wet during the work. Air monitoring was carried out throughout; every result was below 0.01 fibres per millilitre, with the monitoring report retained by the business.

Removing the Underlying Affected Soil

Once the stockpiles were gone, the team excavated approximately 100 millimetres of soil from beneath them as part of the remediation, extending the work beyond the visible piles to the affected ground underneath. The occupational hygienist then visually inspected the exposed subgrade for any remaining visible asbestos and issued an asbestos clearance certificate following the inspection.

Aerial view of the Marsden acreage property cleared and levelled after asbestos soil remediation
After: stockpiles gone, the underlying soil removed and the block levelled ahead of the hygienist’s inspection.

Finishing and Handing Back the Property

The team levelled the block and left the area neat and tidy for the homeowner. The temporary recycled-asphalt access road was retained for the client. The homeowner said they were happy the clean-up had been completed. The result: 3,100 tonnes of contaminated mixed material removed, a levelled site and an asbestos clearance certificate following the hygienist’s visual inspection.

Drone view of excavators finishing the levelled Marsden site after contaminated waste removal
Final levelling from the air.
CAT excavator on levelled ground at the Marsden property after the asbestos cleanup
The block left neat and level, with the access road retained for the owner.

What This Project Demonstrates

Marsden shows Total Asbestos’s combined asbestos-remediation and earthmoving capability. Company-owned machinery and directly employed operators let one team excavate, build truck access and manage loading on the same project, and coordinate all of it with subcontract haulage and the receiving facility despite wet ground and rain interruptions.

Need asbestos-contaminated soil or mixed demolition waste removed?

Illegally dumped material, council clean-up notices and large tenanted blocks are exactly what our asbestos soil remediation service is set up for. Contact Total Asbestos to discuss your site, access conditions and remediation requirements.

Get a Free Site Assessment

Send us the hygienist’s report if you have one, or just tell us what is on the block and how a truck would get to it. We will come out and give you a fixed quote.