Real Projects, Real Numbers

Asbestos Removal Case Studies

How Total Asbestos plans, removes and certifies asbestos-contaminated soil and sites across Brisbane, Logan and Moreton Bay. Photos, tonnages, timeframes and what each job taught us.

Recent Total Asbestos Projects

Soil remediation, friable removal and commercial roof removal: more than 4,100 tonnes of contaminated soil, a shopping centre ceiling cleared overnight and a 730 m² regional roof, each finished with an independent hygienist’s clearance certificate.

CAT 3-tonne excavator levelling a Moorooka backyard after asbestos-contaminated soil removal
Residential, Brisbane southside

Moorooka: Asbestos Soil Left Behind by a Pool Dig

30.9 tonnes of contaminated spoil removed from a restricted-access backyard in one working day, using a 3-tonne excavator, a Bobcat and a skip truck.

30.9 tonnes1 daySeptember 2026
Read the case study →
Aerial view of covered asbestos-contaminated demolition waste stockpiles on a Marsden acreage property before remediation
Residential acreage, Logan

Marsden: 3,100 Tonnes of Illegally Dumped Asbestos Waste

Friable asbestos in soil mixed with timber, brick and concrete, cleared in wet conditions with our own excavators, a temporary access road and ten trucks on rotation.

3,100 tonnes2 weeksJune 2026
Read the case study →
Total Asbestos CAT excavator removing asbestos-contaminated material on a Wakerley construction site
Commercial, Tier 1 builder

Wakerley: The 20-Tonne Job That Was Really 1,000 Tonnes

Contamination was holding up a construction program. A hygienist defined the real scope and two large excavators cleared it in three days.

1,000 tonnes3 daysMay 2026
Read the case study →
Class A asbestos technicians removing a low-density friable asbestos ceiling inside a sealed enclosure at night
Commercial, friable, Class A

Kenmore Village: Friable Asbestos Ceiling Removed Overnight

About 100 m² of low-density asbestos ceiling out of a shopping centre tenancy in one night, under negative pressure, cleared on the first inspection so the centre opened on time.

100 m²1 nightJuly 2026
Read the case study →
Scissor lift and Total Asbestos crew removing the asbestos roof from an unoccupied government building in Maryborough
Commercial, roof, regional

Maryborough: 730 m² Asbestos Roof Removed in Two Days

An eight-person crew stayed overnight in Maryborough to strip a government building’s roof and hand it to the roofing contractor, cleared, on the agreed date.

730 m²2 daysRoofing contractor
Read the case study →
Class A asbestos technician in protective suit removing friable low-density board from the internal linings of a Zillmere house
Residential, Brisbane northside

Zillmere: Friable Linings, Soil Under the Slab and a Pool

A knockdown rebuild cleared by one contractor: friable asbestos board removed, the house demolished, contaminated soil found under the slab and removed, and the pool taken out and backfilled.

450 m²50 tonnesJuly 2026
Read the case study →
Total Asbestos excavator demolishing the steel-framed school building at Currimundi State School after asbestos panel removal
Commercial / education

Currimundi State School: 1,000 m² of Panels Out and the Building Down in a Week

Asbestos infill panels removed and the building demolished inside the April school holidays, with hygienist clearance before demolition and the concrete slab handed back retained.

1,000 m²1 weekSlab retained
Read the case study →
Total Asbestos truck on the barge to Russell Island for asbestos removal at the state school
Commercial / education

Russell Island State School: 700 m² of Panels Off the Island in Four Days

Crew, equipment, skip and waste all moved by barge. A six-person crew stayed on the island, stripped the asbestos panels from two buildings and handed them over cleared, on the demolition contractor’s date.

700 m²4 daysBarge logistics
Read the case study →

Why We Publish Case Studies

Asbestos-contaminated soil is one of the least understood jobs in our industry. Most people searching for help have just been told by a pool builder, landscaper or site supervisor that they have a problem nobody on site is licensed to fix. These write-ups show what actually happens next: how the extent is established, what machinery fits the access, where the material goes, what the hygienist signs off, and how long it takes.

Every figure on these pages comes from the job records: waste tracking certificates, hygienist reports and air monitoring results held by Total Asbestos. If your situation looks like one of these, book a free site assessment and we will tell you which approach applies.