Case Studies / Residential / Moorooka, Brisbane

30.9 Tonnes, One Day

Asbestos Soil Remediation for a Homeowner in Moorooka

Total Asbestos removed 30.9 tonnes of asbestos-contaminated soil from a restricted-access backyard in a single working day, with the occupational hygienist’s visual clearance completed the following morning.

30.9 tAsbestos-contaminated soil removedRecorded across two waste tracking certificates
1 dayRemoval completed on siteFriday 18 September 2026, finished about 4 pm
6 amHygienist visual clearance the next morningAsbestos clearance certificate issued to the homeowner
LocationMoorooka, Brisbane southside
ClientPrivate homeowner
MaterialExcavated soil containing asbestos cement (fibro) sheeting fragments
Quantity removed30.9 tonnes
Removal completed18 September 2026, one working day
CrewTwo machine operators, one asbestos supervisor, one truck driver
EquipmentThree-tonne excavator, Bobcat and skip truck
DisposalBMI at Stapylton, two waste tracking certificates
ClearanceOccupational hygienist’s visual clearance of the rear soil area the following morning

The Challenge: Contaminated Soil Left Behind After a Pool Excavation

A homeowner in Moorooka contacted Total Asbestos to remove asbestos-contaminated soil stockpiled beside a newly completed swimming pool. The soil had come out of the pool excavation and contained asbestos cement sheeting fragments throughout. The pool contractor was not licensed to handle contaminated material, so the pool was finished first and the stockpile was left on site for a licensed removalist to deal with afterwards.

The homeowner knew the asbestos was there and wanted it gone. The real problem was access. The driveway was about three metres wide, but the entry into the backyard narrowed to an estimated 1.5 metres. The stockpile sat at the rear of the property while any removal truck had to stay at the front. Nothing could be loaded straight from the stockpile into a truck.

Asbestos-contaminated soil stockpile behind mesh fencing in a Moorooka backyard before remediation
Before: the pool-excavation stockpile at the rear of the property, fenced off ahead of removal.
Close view of asbestos cement sheeting fragments mixed through a soil stockpile in Moorooka
Asbestos cement sheeting fragments were mixed right through the soil.

Planning the Work Around Restricted Access

Before mobilising, Total Asbestos visited the property to assess the stockpile and the access route. That inspection settled the equipment: a three-tonne excavator and a Bobcat, both narrow enough to pass through the backyard entry, and a skip truck instead of one of the company’s larger semi-trailers.

The job was set up for a four-person crew, two machine operators, an asbestos supervisor and a truck driver, so the team could excavate at the rear, transfer material to the front and load it for removal without anyone standing idle. Before the crew arrived, the homeowner had placed plastic sheeting over the new pool.

Narrow side access path beside a Moorooka house assessed before asbestos soil removal
The side access assessed before work began. It narrowed to about 1.5 metres.
New swimming pool covered with plastic sheeting before asbestos soil removal began in Moorooka
The homeowner’s pool covering in place before remediation started.

Removing 30.9 Tonnes From the Backyard

The three-tonne excavator handled the contaminated soil at the rear of the property. The Bobcat collected the material and ran it along the concrete access path to the skip truck at the front. The layout meant repeated trips and extra handling between excavation and loading, but the crew still completed the removal in one working day.

Water was used throughout to suppress dust. Larger loose asbestos cement fragments were picked up and bagged so machinery would not run over and crush them along the transport route. Barrier tape marked the work zone to restrict entry. Each skip was lined with black plastic before loading; once full, the plastic was folded over the material and sealed for transport.

In total, 30.9 tonnes of contaminated soil were removed and transported to BMI at Stapylton, with the quantity recorded across two waste tracking certificates.

Total Asbestos 3-tonne excavator working the contaminated soil stockpile at the rear of a Moorooka property
The three-tonne excavator working the stockpile at the rear.
Labelled asbestos waste bag used to collect loose asbestos cement fragments on the Moorooka job
Larger loose fragments were bagged rather than left for machinery to crush.

Finishing the Area and Obtaining Clearance

After the stockpile was gone, the crew levelled the rear area with the three-tonne excavator at the homeowner’s request and moved several rocks to leave the yard arranged the way the homeowner wanted it.

Removal work finished at about 4 pm on Friday 18 September 2026. An occupational hygienist attended at 6 am the following morning to carry out a visual clearance inspection. The homeowner received an asbestos clearance certificate following that inspection, covering the rear area where the contaminated soil had been.

Moorooka rear yard levelled and clear after asbestos-contaminated soil removal
After: the rear area levelled, ahead of the next morning’s visual clearance.
Levelled backyard with rocks repositioned after asbestos soil remediation in Moorooka
Final levelling, with rocks repositioned at the homeowner’s request.

The Outcome for the Homeowner

The unwanted stockpile was removed, the yard was levelled and the rear soil area was visually cleared the following morning. The homeowner said they were happy the work was finished.

For Total Asbestos, the job shows the value of assessing access before the truck turns up. Choosing machinery that actually fits the property is what made it possible to remove a substantial quantity of contaminated soil from a confined residential backyard in a single day.

Have asbestos-contaminated soil left behind after an excavation?

This is the most common residential soil job we see: a pool, a retaining wall or a landscaping dig turns up fibro fragments, and the contractor cannot legally remove the spoil. Our asbestos soil remediation service covers the site visit, the right-sized machinery, licensed disposal with waste tracking certificates and the hygienist’s clearance. Contact Total Asbestos to discuss your property, access and removal requirements.

Get a Free Site Assessment

Tell us where the soil is, roughly how much there is and what the access is like. We will come out, measure it up and give you a fixed quote.

Office
49 Loam Street, Acacia Ridge QLD 4110
Hours
Monday to Saturday, 6:30am to 5pm