Case Studies / Commercial / Maryborough, Queensland

730 m², Two Days, Regional

Commercial Asbestos Roof Removal in Maryborough

Total Asbestos removed 730 square metres of asbestos roofing from an unoccupied government building in Maryborough over two days. Following hygienist clearance, the site was handed over to Roof Pro by the agreed deadline for re-roofing.

730 m²Asbestos roofing removedSheets kept wet, wrapped and disposed of at a licensed facility
2 daysOn site, with the crew staying overnight in MaryboroughOne supervisor and seven removalists
On timeHygienist clearance and handover to Roof Pro by the agreed deadlineAir monitoring reported within limits
LocationMaryborough, Queensland (about 250 km north of Brisbane)
ClientRoof Pro (roofing contractor)
BuildingGovernment building, unoccupied during removal
Scope730 m² of asbestos roof removal ahead of re-roofing
Removal durationTwo days
CrewOne supervisor and seven removalists
AccessScissor lift
Regional logisticsCrew travelled from Acacia Ridge and stayed overnight in Maryborough
Work area controlsExclusion zone with asbestos bunting and signage
Dust suppressionWater used to keep the roofing wet during removal
Air monitoringCarried out; results reported within limits
HandoverHygienist clearance, then handover to Roof Pro for re-roofing

The Brief: Asbestos Removal Ahead of Re-roofing

Roof Pro engaged Total Asbestos to remove the asbestos roof from a government building in Maryborough. Roof Pro would then install the replacement roof, so the removal and the clearance were critical steps in the overall roofing program. The building was unoccupied while the removal took place. The scope covered 730 square metres of asbestos roofing, with a defined handover deadline so Roof Pro could proceed.

Weathered corrugated asbestos cement roof on the Maryborough government building before removal
Before: the corrugated asbestos cement roof.
Scissor lift and Total Asbestos crew removing the asbestos roof from an unoccupied government building in Maryborough
Scissor lift access to the roof.

The Challenge: A Regional Job With a Firm Deadline

Alongside the roofing contractor’s deadline, the main logistical challenge was the distance from Total Asbestos’s Acacia Ridge base. Travel and on-site resources had to be coordinated so the whole removal fitted inside a two-day window.

Resourcing the Two-Day Removal

Total Asbestos deployed an eight-person crew, one supervisor and seven removalists, who stayed overnight in Maryborough between the two days rather than returning to Brisbane. A scissor lift provided access to the roof, and the work was organised around the agreed removal period and the hygienist’s attendance so the site could be handed over for the next stage.

Total Asbestos removalist lifting a corrugated asbestos roof sheet on the Maryborough job
Sheets lifted whole and lowered for wrapping.
Asbestos roof sheets partly removed exposing timber battens on the Maryborough building
Battens exposed as the sheets came off in sequence.

Managing the Asbestos Work Area

An exclusion zone was set up with asbestos bunting and warning signage to restrict access, and the building stayed unoccupied throughout. Water kept the roofing wet to suppress dust as the sheets were removed. Air monitoring ran during the project; Total Asbestos reports the results were within limits and no further action was required.

Asbestos roof sheets kept wet with a hose for dust suppression during removal in Maryborough
Roofing kept wet during removal.
Asbestos roof sheets wrapped in plastic and stacked for licensed disposal at the Maryborough site
Wrapped sheets stacked for licensed disposal.

Clearance Before Handover

The 730-square-metre roof removal was completed over two days. A hygienist attended to carry out clearance before Total Asbestos handed the site back to Roof Pro, who then carried out the re-roofing. Total Asbestos’s scope was the asbestos removal and handover; the replacement roof was Roof Pro’s.

Maryborough building roof fully stripped of asbestos sheeting with battens ready for re-roofing
Stripped and cleared for the roofing contractor.
Total Asbestos crew working across the stripped roof battens of the Maryborough government building
The crew finishing on day two.

Meeting the Roofing Contractor’s Program

Total Asbestos met the agreed handover deadline. The eight-person crew, the overnight stay in Maryborough, scissor lift access and coordinated clearance delivered the removal stage inside the required timeframe.

For roofing contractors, Maryborough shows we can slot asbestos removal into a wider roof replacement program, including well beyond our Brisbane base, and hand over a cleared site on the day it was promised.

Coordinating an asbestos roof replacement?

Our asbestos roof removal service works alongside roofing contractors on homes, sheds, commercial and government buildings across South East Queensland and regionally. Contact Total Asbestos to discuss removal scope, access, regional mobilisation and handover requirements for your roofing program.

Talk to Us About Your Roofing Program

Roofing contractors: send us the roof area, location and your re-roof date and we will quote the removal, clearance and handover around it.

Office
49 Loam Street, Acacia Ridge QLD 4110
Hours
Monday to Saturday, 6:30am to 5pm